article · International Journal of Operational Research
Parallel, and serial schedule generation schemes (SGS) are the core of most heuristic solution procedures for the resource-constrained project scheduling problem. The solution-quality of the generated schedules using the two schemes depends on the project's network topology and resource restrictions. According to the most recent publication, the network topology is measured using four indicators: serial/parallel, activity distribution, length of arcs, and topological float, whereas resource restrictions are assessed using two parameters: resource use and resource-constrainedness. The main objective is to investigate the impact of the project's network topology and resource parameters on the performance of the two schemes. A study-based generated datasets has been applied using a genetic algorithm with the two schemes. The computational results demonstrate that out of four indicators, serial/parallel has the most significant impact on distinguishing between the performance of the two SGS schemes. Moreover, resource use also impacts the discrimination between the two schemes.
This page summarises published work. The authoritative version sits with the publisher.
DOI: 10.1504/ijor.2024.142376
Is something wrong with this record? Report it or request removal.
Discussion
Have you built on this work, tried to replicate it, or seen it applied in practice? Share what you know. Verified researchers and MARATTO™ domain experts can open a discussion, and any member can reply. Contributions are reviewed before they appear.
No discussion yet. Open the first thread.
New to MARATTO™? Create a free account.